lUnwinding turret:
Tension force control of unwinding.
1) Permanent tension brake, magnetic powder detent
2) Unwinding positive feeding structure, transducer sends out material on average speed
3) Control mode: computer instruction, dancing roller displacing sensor controls roll sending out speed
4) Fixed taper cone nip unwinding shaft (air expanding shaft)
Edge position control (EPC)
1) Configuration: screw mandrel secondary control, unwinding turret movement
2) Control modality: reflection electric potentiometer sensor testing, independent control.
3) Tracking accuracy: 0.5mm
4) Adjustment range: 150mm
lFolding section
1) Configuration: two sides folded at same time, one side adjustable
2) Adjustment: manual regulation
lVertical sealing setup:
1) Configuration: vertical disposition iron pressing, cooling assembly spring pressing structure
2) Drive: main electric machinery drives coupling rod of eccentric mechanism to do curve motion
3) Quantity: One team on vertical thermal sealing, one team on cooling, two teams on vertical shaping.
4) Length: 800mm
lHorizontal sealing setup:
1) Configuration: horizontal disposition iron press assembly spring structure, cooling assembly
2) Drive: main electric machinery drives coupling rod of eccentric mechanism to do vertical motion
3) Quantity: three teams on thermal sealing, one team on cooling
4) Length: 350mm
lFilm feeding device
1) Configuration: pneumatic pressing rubber roller friction type (pneumatic parts using KOGANEI from Japan)
2) Drive: imported fully digital runoff production servo mechanism (Servo motor 1.5Kw, Panasonic Japan)
3) Transmission: synchronous band and wheel
4) Control modality: centralized computer control, synchronous length fixing and automatic photoelectrical tracking system)
lMiddle tension
1) Configuration: dance roller tension force structure, set signal
2) Control modality: centralized computer control
3) Mechanism of control: complementary trend of dance roller tension movement control the middle servo step length to achieve stop and begin at the same time
4) Testing form: electromagnetism approaching switch (NPN)
5) Adjustment range of tension force: 0.1-0.2mm (computer setting, automatic reciprocate)
lMain transmission device
1) Configuration: crank rocker push pulling coupling rod structure
2) Drive: Germany SEW motor 1.5KW as main motor, work more steady, reliable and efficiency.
3) Transmission: main transmission electric machinery band 1: 10 high strength toothed gear speed reducer
4) Control modality: centralized computer control
5) Movement mode: main motor running drives frame to do vertical movement
lAutomatic positioning device
1) Testing form: tracking testing of reflection photoelectrical sensor
2) Testing accuracy: 0.01- 0.25mm
3) Integrative positioning accuracy: ≤0.5-1mm
4) Photoelectrical searching range: ±3mm
5) rectifying equalizing range: ±3mm
6) positioning rectifying method: servo tracks current compensating, photoelectrical automatic movement rectify system
lTemperature control setting:
1) Testing form: thermocouple test
2) Control modality: independent control, PID adjustment, solid state relay
3) Temperature setting range: normal temperature and up to 360℃
4) Temperature testing point: middle part of electric heater, keep temperature even
lCutting knife
1) Configuration: upper cutting knife + adjustment equipment + fixed bottom cutting knife
2) Form: spring shear knife
3) Transmission: main motor driving, eccentric mechanism vertical movement
4) Adjustment: horizontal movement (double end)
lPunching equipment (using imported parts)
1) Configuration: embowed set supports pneumatic engine lead to main model impact structure
2) Control modality: centralized computer control
3) Drive: Solid-state relay drives electromagnetic valve
4) Quantity of punching set: generally configures one team
5) Air cylinder: Taiwan Airtac
6) Model: rhombus 1 set
lWelding knife setup:
Vertical: 20mm*1
Horizontal: 10mm*3
lSupporting facilities (Please settle it by client selves)
1) power supply: three-phase 380V, ±10%, 50HZ five wiring system
2) volume: 20KW
3) air supply: pressure ≥ 0.6Mpa 35 m / min
4) cooling water: 3 L / min
Performance
lUnwinding turret:
Tension force control of unwinding.
1) Permanent tension brake, magnetic powder detent
2) Unwinding positive feeding structure, transducer sends out material on average speed
3) Control mode: computer instruction, dancing roller displacing sensor controls roll sending out speed
4) Fixed taper cone nip unwinding shaft (air expanding shaft)
Edge position control (EPC)
1) Configuration: screw mandrel secondary control, unwinding turret movement
2) Control modality: reflection electric potentiometer sensor testing, independent control.
3) Tracking accuracy: 0.5mm
4) Adjustment range: 150mm
lFolding section
1) Configuration: two sides folded at same time, one side adjustable
2) Adjustment: manual regulation
lVertical sealing setup:
1) Configuration: vertical disposition iron pressing, cooling assembly spring pressing structure
2) Drive: main electric machinery drives coupling rod of eccentric mechanism to do curve motion
3) Quantity: One team on vertical thermal sealing, one team on cooling, two teams on vertical shaping.
4) Length: 800mm
lHorizontal sealing setup:
1) Configuration: horizontal disposition iron press assembly spring structure, cooling assembly
2) Drive: main electric machinery drives coupling rod of eccentric mechanism to do vertical motion
3) Quantity: three teams on thermal sealing, one team on cooling
4) Length: 350mm
lFilm feeding device
1) Configuration: pneumatic pressing rubber roller friction type (pneumatic parts using KOGANEI from Japan)
2) Drive: imported fully digital runoff production servo mechanism (Servo motor 1.5Kw, Panasonic Japan)
3) Transmission: synchronous band and wheel
4) Control modality: centralized computer control, synchronous length fixing and automatic photoelectrical tracking system)
lMiddle tension
1) Configuration: dance roller tension force structure, set signal
2) Control modality: centralized computer control
3) Mechanism of control: complementary trend of dance roller tension movement control the middle servo step length to achieve stop and begin at the same time
4) Testing form: electromagnetism approaching switch (NPN)
5) Adjustment range of tension force: 0.1-0.2mm (computer setting, automatic reciprocate)
lMain transmission device
1) Configuration: crank rocker push pulling coupling rod structure
2) Drive: Germany SEW motor 1.5KW as main motor, work more steady, reliable and efficiency.
3) Transmission: main transmission electric machinery band 1: 10 high strength toothed gear speed reducer
4) Control modality: centralized computer control
5) Movement mode: main motor running drives frame to do vertical movement
lAutomatic positioning device
1) Testing form: tracking testing of reflection photoelectrical sensor
2) Testing accuracy: 0.01- 0.25mm
3) Integrative positioning accuracy: ≤0.5-1mm
4) Photoelectrical searching range: ±3mm
5) rectifying equalizing range: ±3mm
6) positioning rectifying method: servo tracks current compensating, photoelectrical automatic movement rectify system
lTemperature control setting:
1) Testing form: thermocouple test
2) Control modality: independent control, PID adjustment, solid state relay
3) Temperature setting range: normal temperature and up to 360℃
4) Temperature testing point: middle part of electric heater, keep temperature even
lCutting knife
1) Configuration: upper cutting knife + adjustment equipment + fixed bottom cutting knife
2) Form: spring shear knife
3) Transmission: main motor driving, eccentric mechanism vertical movement
4) Adjustment: horizontal movement (double end)
lPunching equipment (using imported parts)
1) Configuration: embowed set supports pneumatic engine lead to main model impact structure
2) Control modality: centralized computer control
3) Drive: Solid-state relay drives electromagnetic valve
4) Quantity of punching set: generally configures one team
5) Air cylinder: Taiwan Airtac
6) Model: rhombus 1 set
lWelding knife setup:
Vertical: 20mm*1
Horizontal: 10mm*3
lSupporting facilities (Please settle it by client selves)
1) power supply: three-phase 380V, ±10%, 50HZ five wiring system
2) volume: 20KW
3) air supply: pressure ≥ 0.6Mpa 35 m / min
4) cooling water: 3 L / min
Modality | Center Sealing, four side Sealing, Double servo (feeding motors are servo), Double inverter. |
Material | BOPP, CPP, PET, nylon and etc plastic laminated film, multilayer coextrusion films, pure aluminum, plating aluminum laminated film, paper plastic laminated film |
Highest bag making speed Normal speed | 180 time/min 30-150 time/min |
Highest material sending out line speed | ≤40 m/min
|
Size of bag | Width: 55-320 mm Length: 500 mm (6 times skip function) |
Width of sealing | 5-50 mm |
Bag style | Center Sealing bag with Max width 320mm, four side seal bag |
size of material roll | Ø 600*840 mm |
Positioning accuracy | ≤±1 mm |
Hot sealers | One team on vertical thermal sealing, one team on cooling, two teams on vertical shaping, Three teams on horizontal thermal sealing, one team on horizontal cooling; |
Temperature control quantity | 11 routes |
Temperature control setting range | 20-360℃ |
Power of whole machine | 25KW |
Overall dimension ( length*width*height ) | 9800*1500*1700 |
net weight of whole machine | About 3800Kg |
Color | Main machine body in black, apple green in enclose |
Noise | ≤75db |
Modality | Center Sealing, four side Sealing, Double servo (feeding motors are servo), Double inverter. |
Material | BOPP, CPP, PET, nylon and etc plastic laminated film, multilayer coextrusion films, pure aluminum, plating aluminum laminated film, paper plastic laminated film |
Highest bag making speed Normal speed | 180 time/min 30-150 time/min |
Highest material sending out line speed | ≤40 m/min
|
Size of bag | Width: 55-320 mm Length: 500 mm (6 times skip function) |
Width of sealing | 5-50 mm |
Bag style | Center Sealing bag with Max width 320mm, four side seal bag |
size of material roll | Ø 600*840 mm |
Positioning accuracy | ≤±1 mm |
Hot sealers | One team on vertical thermal sealing, one team on cooling, two teams on vertical shaping, Three teams on horizontal thermal sealing, one team on horizontal cooling; |
Temperature control quantity | 11 routes |
Temperature control setting range | 20-360℃ |
Power of whole machine | 25KW |
Overall dimension ( length*width*height ) | 9800*1500*1700 |
net weight of whole machine | About 3800Kg |
Color | Main machine body in black, apple green in enclose |
Noise | ≤75db |